Thursday, April 24, 2008

Utility Easements

I wish we would have had a good idea about what the city required as far as utility easements from our neighbors before our review meeting. I might have been able to thwart the conversation that took us down a path of needing more review time. Oh well.

Turns out we only need to have our neighbors sign a letter of intent addressed to Steve Olt indicating that they would grant the city the needed utility easement to provide utilities from the church development on the corner to our lot.

We know our neighbors are amenable to this so we'll just need to get a letter signed by them and call it a day. We'll have that for our utility meeting on 4/30.

Lesson learned.

Ditch Co Comments

We've been working with the ditch company and with the Blehm Water Association to ensure that we continue to get our water once we're not in the Blehm subdivision any longer. John Baum, the president of the Blehm Water Association, was ok with us staying in the organization to manage our water. That is good.

The ditch company (John Moen) has been telling us all along that he really doesn't care what we do with our private laterals.

I've wondered why JR Engineering put the ditch company signature on the plat drawings, but probably because there are ditch easements on our property. That's fine.

We got a comment on our submission to the city from Gene Fischer, the ditch company attorney that they would need a $500 review fee. Yikes. Just to look at the drawings and sign something that doesn't affect them in any way. In addition to the fee, we have to have a letter from our engineer stating that the ditch head gate is not on our property and that the property is serviced by private laterals. Ugh.

I wonder where the head gate is? We should probably find out. Which reminds me, our water is coming soon. We haven't heard from John Baum about when exactly and which days we have to put water on our pasture. Miles met with a friend, JD, who has ditch water so he could give us advice as to how to get our water on the back part of the pasture. We don't want to raise our ground water level on the portion that we plan to build the house on.

Wednesday, April 16, 2008

The Subdivision Meeting

My parents are on vacation, so we planned to take the boys to the drop-in daycare during our meeting. Turns out that the daycare didn't open until 8:30AM - the exact time our meeting with the city was supposed to start. We decided to bring the boys with us and hope they behave. We had plenty of paper and pens that they could play with during our meeting, so hopefully they will have enough attention span to hang with us.

Our meeting started out great - no real hurdles for comments yet. Susan Joy attended from Engineering (instead of Randy Maizland) and started off with very good news. They had been working internally and decided that they would not require us to do the design and escrow of the money for the Kechter Road improvements. Yea! Save us a lot of money (~$24k) and headache of designing something that may not happen for awhile. It would also save us time as they were going to push through to public meeting without another review with the city!

Miles had to leave to entertain the boys while I attended the rest of the meeting.

Justin Fields from Light & Power attended instead of Janet McTague. Justin had some concerns with the power coming from the church property. Janet explained to us that we could ask for easements from Helen and Judy, but that it wouldn't be required because they could just pull it from the current Kechter ROW. Turns out that Justin wasn't so keen on that. We discussed possibly using the REA easement down the middle. But, I knew that both our neighbors were amenable to putting easements across their property. Then discussion went to the ditch easement and the private laterals that run through all of our properties. They don't know if the ditch and the utility easements can be in the same piece of ground, so something that Steve Olt said he'd research for us. In addition, we know that Helen is concerned about the big tree that will likely fall right in the easement. We didn't come to a resolution on this, so Susan started getting concerned.

As the comments started coming forth, Susan had second thoughts about not going through another round of review - darn! So, we'll have to resubmit in a few weeks after we resolve all the issues. She also mentioned that after thinking about it a little more, traffic operations may require us to install the sidewalk along Kechter as part of this project. Ugh.

Drainage was also a concern at the meeting, but we indicated that no changes to the historical flows will be made as part of the subdivision. We are going to pull all the drainage lines back onto our property and deal with the detailed lot grading plan for lot 2 with the building permit.

None of the other comments were really that big. A few typos and wording changes, but other than that looks pretty straight forward.

Next steps are to attend a utility coordination meeting (because of the ditch, power and easement discussion) and plan to resubmit for another round of staff review.

Tuesday, April 1, 2008

Sub-Division Submittal

On April 1, 2008, we finally submitted the paperwork for our subdivision. We're hoping that there won't be many comments and that we can get through this process fairly quickly. Now that we've decided on a builder and an architect/designer, I am more anxious than ever to get this project moving a little faster.