- The windows have been delivered. One was broken and one is damaged.
- The duct work and air handler are in for the main floor.
- There are some holes drilled for sinks and toilets.
- We have some tub color samples for the upstairs tubs.
- The trusses are complete for the dormers and the roof is all sheated.
- They're having a hard time trying to figure out how they are going to get the stairs to the bonus room worked out since the engineers added a steel beam in the mud room.
- The back porch and back roof support beam is in.
We're meeting Wayne out there tomorrow at lunch to review a few things so will get picture updates tomorrow.