Hi Susan,
Thanks for speaking with me yesterday. I'm just following up on our conversation so that I can give an update to our attorney and the title company.
As I understand it:
- The utility and plat mylars were dropped off at the city on Thursday, October 23 (see attached).
- As of yesterday, November 3, none of the utility signatures have been completed. Seems to me like 7 business days should be enough time? What is the hold up?
- The DA was on Sheri's desk for final approval and then going to the city attorney yesterday afternoon.
- Sheri mentioned at the development workshop Steve hosted about the Kechter / Trilby area, that the DA should take about 3 weeks. I sent the DA information on Thursday, September 11. Seven weeks is 4 weeks longer than the average length. Do you know what the hold up was with this agreement? I assume we will get the final for our signature this afternoon, tomorrow at the latest?
- I will wait to hear from you that the utility drawings have gone to JR Engineering for final signature and copies before I get our attorney and title company scheduled again to complete the process and record the plat.
- Miles and I will ensure that the DA is signed and sent back to you within 1 business day of receiving it from you. I assume this only needs to be notarized and no other signature is required?
I think that's it. Please let me know either by phone (303) 588-6086, or by e-mail when the utility drawing signatures are completed. Again, I would be happy to pick them up and take them over to JR Engineering if you need me to.
Thanks,
Jennifer
Tuesday, November 4, 2008
Can We Just Get This Over With?
Here's a copy of an e-mail I sent to the city today. This just sums up where we are, ugh!!